Effingham County Approves Moon River Studios Master Plan

Staff Report From Savannah CEO

Friday, July 24th, 2015

FONU2, Inc. announced today that the Effingham County Board of Commissioners ("Commission") has approved the Company's Master Plan to develop a 1,560 acre full service film production facility. The approval by the Commission is another significant milestone that has been achieved, and was a necessary step prior to construction permits being issued. This follows a critical path that has been created by the Company's management team and its civil engineers. The milestones and dates completed include:

Survey for Water Line

April 2, 2015 

Updated Master Plan (submission)

April 13, 2015

Survey for Spine Road

April 15, 2015 

Engineering Design for Water Line (submission)

April 16, 2015

Topo Survey for Studio Site (57 + acres)

May 13, 2015

Septic System Drain Field Survey (3+ acres)

June 1, 2015

Septic System Soil Investigation

June 14, 2015   

Engineering Design for Spine Road (submission)

June 15, 2015 

Revised Master Plan (submission)

July 8, 2015   

Further Revised Master Plan (submission)

July 14, 2015

County Commission Approval of Master Plan

July 21, 2015

"This is an important project for the county and we are very excited to see the master plan approved," stated Rick Lott, Executive Director of the Effingham County Chamber of Commerce. "This project is led by a hard working, down-to-earth team, and Moon River Studio's success will have a profound effect on economic development for the region. I congratulate the team on this latest milestone."